EN 1090 — CE Marking for Steel Structures: Complete Guide

Introduction

The European standard EN 1090 establishes the requirements for the execution of steel and aluminium structures in the European Union. Since 1 July 2014, CE marking has been mandatory for all structural metallic components placed on the European market. Any company manufacturing steel structures — from a simple industrial gate to a bridge — must comply with this standard.

---

Structure of EN 1090

PartTitleScope
EN 1090-1Conformity assessmentCE marking requirements, FPC, declaration of performance
EN 1090-2Technical requirements for steelExecution classes, welding, preparation, erection
EN 1090-3Technical requirements for aluminiumSimilar to part 2 for aluminium

---

Execution Classes (EXC1 to EXC4)

ClassLevelExamplesWelding requirements
EXC1BasicAgricultural structures, simple roofingQualified welders ISO 9606-1
EXC2StandardCommercial buildings, industrial hallsQualified WPS (ISO 15614-1), 100% visual inspection
EXC3DemandingBridges, towers, fatigue-loaded structuresISO 3834-2, mandatory NDT, IWE/IWT coordinator
EXC4MaximumNuclear, offshore structuresISO 3834-2+, third-party inspection

---

Welding Requirements by Class

RequirementEXC1EXC2EXC3EXC4
Welders ISO 9606-1✅✅✅✅
Qualified WPS ISO 15614-1❌✅✅✅
Welding coordinator❌IWSIWT/IWEIWE
ISO 3834Part 4Part 3Part 2Part 2+
Visual inspectionSampling100%100%100%
NDT❌Sampling 5-20%20-100%100%
ISO 5817 levelDCBB+

---

ISO 3834 — Welding Quality System

ISO 3834LevelExecution classes
ISO 3834-4Elementary requirementsEXC1
ISO 3834-3Standard requirementsEXC2
ISO 3834-2Comprehensive requirementsEXC3, EXC4

---

Welding Coordinator (ISO 14731)

ClassMinimum qualification
EXC1Not mandatory
EXC2IWS — International Welding Specialist
EXC3IWT or IWE
EXC4IWE — International Welding Engineer

---

CE Marking and FPC

CE marking under EN 1090-1 requires: initial type testing (ITT), factory production control (FPC), certification by a notified body, declaration of performance (DoP), and CE marking on the product/documentation.

FPC covers raw material control, consumables, personnel qualification, equipment maintenance, traceability, inspection and non-conformity treatment.

---

How to Obtain Certification

The typical process takes 6 to 12 months: define execution class, implement ISO 3834, qualify welders (ISO 9606-1), qualify procedures (ISO 15614-1), appoint coordinator, implement FPC, audit by notified body.

Cost: between €5,000 and €30,000 depending on class, company size and number of processes.

---

Quick Summary

If your company...You need...
Makes gates, railings, guardsEXC1 — ISO 3834-4, welders ISO 9606-1
Makes buildings, industrial hallsEXC2 — ISO 3834-3, qualified WPS, IWS
Makes bridges, towersEXC3 — ISO 3834-2, IWT/IWE, NDT
Makes nuclear or offshore structuresEXC4 — ISO 3834-2+, IWE, 100% inspection

---

*Article based on EN 1090-1:2009+A1:2011, EN 1090-2:2018, ISO 3834, ISO 14731, EN 1993-1-1. Published at WeldFC Academy.*